At the end of July, the Dedham-Westwood Water District’s contractor, Primetime Development, started installing a new section of water main on a portion of Schoolmaster Lane between 100 Schoolmaster Lane and Country Club Road.
The project consists of installing 1,325 linear feet of new water main, connecting it to the existing water mains at each end, installing fire hydrants and valves, and constructing new water services to each property within the work limits.
This project was highlighted as a high priority project in the district’s 2020 Capital Improvement Plan and will ultimately provide benefits to both the towns of Dedham and Westwood, as well as to all residents on Schoolmaster Lane by providing:
While construction is underway, Schoolmaster Lane will remain open to residents and local traffic (mail delivery, trash pickup, visitors, etc.). However, intermittent delays will likely occur near the work zone. Police will be on-site during work hours to provide assistance. Due to the rocky terrain, heavy equipment will likely generate noise and vibration during work hours.
At times, residents who currently receive water from the District will have their water service temporarily disrupted. The District will notify affected residents 24 hours before any planned water disruptions. Sudden water disruptions are unplanned emergencies, and unfortunately, the District cannot notify customers in advance.
Residents are strongly encouraged to sign up for project email updates. The District will send routine communications weekly and, when feasible, emergency notifications.
Anticipated Construction Schedule for the Week of August 24-28, 2026:
Please Note: All construction activities are anticipated and may be changed due to weather or in-the-field changes.
Anticipated Traffic Impacts & Work Hours:
A one-lane alternating traffic pattern will be in effect. Police will be on-site to assist vehicles and pedestrians. Anticipated work hours are Monday through Friday, 7 a.m. to 4 p.m.
Please check back!